What is the purpose of early contractor involvement?
What is the purpose of early contractor involvement?
Early contractor involvement (or ‘ECI’) is a method of construction contracting that allows a builder to become involved, and potentially start work, before the design has been completed.
What is an ECI model?
Early contractor involvement (ECI) is an approach to contracting that can complement either a traditional or novated design and build delivery model. ECI can be used to gain early advice and involvement from a contractor into the buildability and optimisation of designs.
Is ECI a procurement method?
Despite numerous industry reports, uptake of the recommendations has been very limited to date. ECI as a procurement route is a key facet of the UK Government Construction Strategy through to 2020 (Cabinet Office 2016), presenting an immediate opportunity for industry to review and benefit from research undertaken.
What does ECI stand for construction?
PRINCIPLE: Procuring agencies will assess the early contractor involvement (ECI) procurement model as part of the procurement options analysis on complex major infrastructure projects, where there is significant unknown scope, risks or interfaces, or a need for accelerated delivery timeframes.
What is the ECC contract commonly known as?
NEC3: Engineering and Construction Contract (ECC) The NEC3 Engineering and Construction Contract is the core document from which the options A-F are extracted. It contains all core clauses and secondary option clauses, together with the schedules of cost components and forms for contract data.
What is ECI and what is its chief advantage to the contractor and client?
ECI enables appointment of a Contractor before details of the project have been fully developed, allowing the Contractor to contribute to design development and planning of the construction phase. Through use of ECI the importance of the Contractor, who is an expert in delivery of construction projects, is recognised.
What are the methods of ECI?
Methods of ECI Contract ECI Contract refers to contractor engagement early in the project development process, which can occur through a variety of methods such as alliancing, management contracting, Integrated Project Delivery (IPD), or even a conditional two-stage contract in a construction project.
What is EPC contractors?
An engineering, procurement and construction contract (EPC contract) is an all-inclusive contract framework, which requires the contractor to complete an agreed scope of work by an agreed completion date, in return for an agreed lump-sum contract price.
What is a GMP contract in construction?
GMP stands for the guaranteed maximum price. That refers to the highest amount of labor, materials and profit costs the contractor can charge the customer in the construction industry.
What does early works mean in construction?
An early works letter is a practical way to get started on a project before the formal contract is finalised. Properly prepared, an early works letter will give both parties protection before the final contract is put in place.
What is 2 stage tendering?
Two-stage tendering involves an initial information stage, facilitating early collaboration between client and contractor. For most projects, and especially for those that are more complex, it is useful to obtain input before there is sufficient information available for the main contract.
What is the meaning of lump sum contract?
What Is a Lump Sum Contract? Under a lump sum contract, also known as a stipulated sum contract, the project owner provides explicit specifications for the work, and the contractor provides a fixed price for the project.
What is the default payment period under the ECC contract?
Under the NEC3 ECC, the Employer had to pay it within 4 weeks after the Contract Date or within four 4 weeks of the later of the Contract Date and the provision of the advanced payment bond.
How many main options can be included in any ECC contract?
Within the ECC contract there are six family level options, from which the Employer is to choose the most suitable and offer the best option/value for money on that project: Option A: Priced contract with activity schedule.
What is NEC 4 contract?
The NEC4 Alliance Contract is a multiparty contract for the appointment of a number of partners to create an alliance to deliver a major project or programme of work.